It just so happened that they try to bring up boys strong and courageous, but ...
![Work on yourself: how to be affectionate and gentle How to make your husband be affectionate](https://i1.wp.com/assol-club.net/wp-content/uploads/2018/03/%D0%BA%D0%B0%D0%BA-%D1%81%D0%B4%D0%B5%D0%BB%D0%B0%D1%82%D1%8C-%D0%BC%D1%83%D0%B6%D0%B0-%D0%BD%D0%B5%D0%B6%D0%BD%D1%8B%D0%BC-2.jpg)
The ideal option is when the calculation of the drainage system is thought out even at the stage of drawing up a general project: this will allow fulfilling the technical requirements, according to which the installation of gutters is carried out before laying the roofing material. However, it often happens that this procedure is carried out already on the finished roof, which is associated with a number of difficulties.
Installation of the gutter system hooks only on the frontal board is possible in cases where the ventilation of the under-roof space is carried out using special holes in the overhangs filing - the so-called. "Perforated spotlights". This is the simplest and most inexpensive type of ventilation, but its efficiency leaves much to be desired.
For a more complete air flow, a gap is used under the crate. This implies a lower position of the frontal board and fixing the brackets exclusively to the crate. The disadvantage of this method is the risk of board collapse under snow load. The decision on the appropriateness of one or another approach to the installation of gutters is made by the owner of the house.
Another reason for installing drainage hooks on the frontal board is to carry out the installation of drainage structures after the completion of the main construction work. A common situation when an unfinished house with an expensive roofing is purchased: in order not to start a laborious procedure for dismantling it, it is easier to fix the gutters to the frontal board. The same algorithm of actions is chosen when replacing the drainage system.
The third reason why the brackets can only be installed on the surface of the frontal board is the use of an anti-condensation waterproofing film. As the installation rules state, it must necessarily go to the eaves overhang, which implies the possibility of installing gutters exclusively on the frontal board.
The installation instructions for the drainage system require the use of special mounting hooks. According to building codes, they can be installed on solid battens (soft roofs), on the surface of the rafters or on the outside of the wind board.
There are seven main ways to install a gutter:
As a result, we can say that the degree of fastening reliability directly depends on the correct installation of the gutter. It should be understood that the gutter is not designed to effectively withstand the snow load: this is the task of the snow guards and special heating cables.
The technology of installing gutter hooks on the finished roof requires a closer look.
To calculate the required number of drainage elements, use the formula (B + H / 2) x C
Explanation of designations:
All parameters are indicated in meters.
The procedure for installing drainage elements on the surface of the wind board:
The gutter is installed in the following sequence:
The connection of modern metal gutters takes place using sealing clamps. Clips, rubber seals and cold welding can be used to connect plastic gutters. During these procedures, it is important not to forget about linear expansion compensation.
You can also use special grates for the drainage system to clear the flowing water from various debris that falls on the roof surface from nearby trees (branches, leaves, needles). In the event of blockages, drainpipes begin to clog, which in winter is fraught with freezing of water inside the drainage, with the threat of rupture.
First of all, you need to decide on which wall it is better to install them on, and which mounting method will be optimal in this case:
It is best if the installation of the vertical fasteners of the drainage system is carried out during the construction of the walls.
If the installation is carried out on finished walls, the following rules should be observed:
Brick walls are equipped with plastic dowels, into which screws fastened with a clamp are screwed. It is more convenient to mount on wooden walls with special rods or plates with self-tapping screws.
How is the vertical type gutter system attached:
It is advisable to place the corner pipe closest to the eaves overhang at a distance of 150 mm from the corner of the building.
A properly executed roof reliably protects the building from moisture penetration into a residential attic or a cold attic. Flowing down its slopes, water can fall on the walls and foundation of the building. To prevent this, the roofing system must be supplemented with an effective drainage system. To ensure the normal operation of such a system, it must be correctly calculated and installed. All this can be done independently, but first you need to familiarize yourself with the technology for performing work and the recommendations of specialists.
Before you start installing the drainage system, you need to decide whether you will buy industrial gutters or make them yourself. If you have certain skills, then all the elements of the drainage system can be made by yourself. For this, galvanized steel is usually used. But they resort to this method quite rarely, since in addition to certain abilities and experience, it will require a significant investment of time and labor. It is much easier to buy finished products and install them yourself.
According to the material of manufacture, drainage systems are divided into two types.
Plastic gutter systems are widely used due to their resistance to corrosion, light weight and ease of installation.
A metal gutter system is heavier than a plastic one, but it has a longer service life.
This is not to say that this or that drainage system is better, it all depends on the operating conditions and the region in which the building is located. The plastic system has a large number of various elements, so it is more convenient to use it when creating a system of complex configuration. Metal gutters look beautiful, last a long time, but their installation is more difficult.
It is easier to install the drainage system before laying the roofing material. For the correct implementation of this work, you must adhere to the following recommendations.
If the length of the building is less than 12 m, then the slope of the gutters can be made in one direction, otherwise it is necessary to mount the gutters with an inclination from the center of the wall to each of its corners
The edge of the gutter must be at least 3 cm below the plane of the roof, otherwise it can be ripped off during the snow sliding
In no case should you cut a polymer-coated gutter with a grinder
When connecting the gutters between them, it is necessary to leave an expansion gap for thermal expansion of the material.
When performing an independent installation of the gutter system, you will need the following set of tools:
Usually, the installation of the gutter system is carried out during the construction of the building, before the installation of the roofing material. Let's consider the sequence of these works in more detail.
It is imperative to install a protective mesh on the funnel, otherwise the drain pipe will be clogged with debris
Depending on the type of gutter, the type of bracket is selected
If the length of the elbow is not enough, then an additional piece of pipe is installed between it and the drain pipe
The maximum distance between the riser mounts cannot exceed 2 m
Clamps consist of two arcs that cover the pipe and tighten it with clamps
Correct installation of window sills is of great importance for protecting the house from moisture. These are metal or plastic slats that are mounted from the outside of the house to the lower part of the window opening.
Ebbs are made of galvanized steel with a polymer coating or plastic
Each window must have an ebb, which is also popularly called the outer window sill. In addition to protecting the walls from moisture penetration, they also give the house a beautiful and complete look.
The ebb installation sequence consists of several steps.
The length of the ebb is standard, and its width is selected for each window sill separately
For reliable fixation of the ebb, the screws are installed in increments of 40–45 cm
The ebb should be tilted away from the window so that water can drain well from it
During the installation of the ebb tide, it is necessary to ensure that its side bends go under the slopes so that water does not fall on the wall. It is recommended to install ebb tides before external slopes are formed.
Before proceeding to fixing the hooks, it is necessary to make markings to ensure the angle of inclination of the gutter system. Due to the slope, the water will drain towards the riser and be effectively removed from the roof.
Installation of hooks under the gutters is carried out before laying the roofing material. This is due to the fact that they are installed under the roof and after it has been laid, long hooks cannot be fixed.
The installation sequence for long hooks will be as follows.
If only short hooks are available, then there is no big deal. Their installation is carried out in the same way, but if in the first case the hooks were attached to the crate or rafters, then here they are fixed to the end plane or to the cornice board.
Short hooks can be mounted after the roofing material has been laid
Short hooks are usually installed after the roof has been installed. Universal holders can also be used, which can be attached as short or long hooks if required.
If you carelessly approach the design and installation of the drainage system, you can make certain mistakes, because of which it will not be able to fully perform its functions:
The structure of the internal drainage system includes the following main elements:
In order for this system to work at any time of the year, water intake funnels must not be installed next to the outer walls of the house, otherwise they will freeze in winter.
The installation of the internal drain is carried out in a certain sequence.
The internal drainage system is usually set up on flat roofs, where there is no natural drainage of water due to the slope of the slopes.
Indoor gutters should be fixed at maximum every 3 m.
Horizontal pipes of the internal drainage system are mounted in the same way as sewer pipes, but with a smaller slope.
Internal drainage systems can be of the following types:
The system for external drainage of water from the roof can be:
When creating an external gutter, the gutters are attached using special brackets, which you can make yourself, but it is better to purchase ready-made ones.
When creating an external gutter, the gutters should be mounted at a slope, this will ensure effective drainage of water entering from the roof. It is not difficult to create an external drainage system with your own hands. All the necessary items are now on sale. It is enough to draw up a diagram and calculate how many and what elements are needed, after which you can simply and quickly install them.
It is quite possible to mount an external drainage system with your own hands, because all the necessary components are on sale to facilitate this process
Installation of the outdoor drainage system is carried out in the following order.
During installation, all connections must be made tight so that water from pipes and gutters does not fall on the walls of the house
For the funnel, a hole is made in the gutter, the edges of which are well cleaned to obtain an airtight connection
A properly executed external drainage system reliably protects the roof, walls and foundation of the building from water penetration into them. During the cold season, during frequent thaws, the drain pipes of the gutters can freeze, so the water will not be efficiently removed. To avoid such a problem, you can install heating of these elements. For this, a self-regulating or resistive cable is used, which is attached to gutters and pipes. Electric current passing through the cable causes it to heat up, as a result of which the elements of the drainage system remain warm, so the water in them does not freeze.
The main requirements for the drainage system are the removal of water from the roof of the house, as well as high strength, tightness and long service life. It is necessary to reckon that such a system can withstand heavy loads; in winter, a large amount of ice can accumulate on it. In order for a self-installed system to meet all the requirements, it is necessary to correctly calculate it, and then carry out the installation in compliance with the developed technologies.
The system for collecting rainwater from the roof slopes and draining it into the storm sewer, or at least further from the foundation of the house, is mandatory for arrangement, therefore it must be included in the future construction project being developed. Most often, the installation of gutters is carried out at the stage of creating the lathing for further roofing. However, there are roof structures that involve fastening the drainage systems after roofing work. In addition, other situations occur, for example, the need to replace dilapidated gutters and pipes with appropriate fasteners.
How to install gutters if the roof is already covered
So, we solve the problem - how to install gutters if the roof is already covered. And the decision is facilitated by the fact that the manufacturers of drainage systems, having foreseen different cases in which it is necessary to mount a common structure, make them in different versions. They will be discussed below.
Not so long ago, the most popular and, perhaps, the only material available for the manufacture of drainage systems was galvanized steel, from which they, by the way, are still produced today. But they are gradually being replaced by metal structures with a polymer coating, or completely made of plastics. Such systems have a more respectable appearance and a long service life, significantly exceeding the durability of conventional galvanized options. Thanks to these qualities, the “new generation” gutters quickly became very popular among buyers.
Since consumers often have a question about which option is better - ordinary galvanized, metal, polymer-coated or completely plastic, there are a few words about their comparative characteristics. It should be noted right away that each from materials from which gutters are produced, there are advantages and disadvantages.
Plastic brackets for gutters have a wide fastening surface, so they fit snugly against the wind board and are securely held on it. However, plastic cannot be bent into the desired configuration like metal brackets. Therefore, all structural details must be precisely adjusted to the specific width of the frontal board and overhang.
The cost of a plastic drainage system exceeds the price of structures made of other materials - this can be called the most significant of their disadvantages.
However, steel parts with a polymer protective coating are not particularly resistant to mechanical scratching. Well, damage to the polymer coating leads to corrosion processes, which means that the duration of the structure's functioning is reduced. It is quite easy to damage the coating even during installation work. Need extra care when assembling and handling fasteners.
The advantage of metal systems is that some of their parts can be much more easily adjusted to certain configurations, for example, by slightly bending the brackets in the right places, which cannot be done with plastic.
You can also casually recall the less popular materials from which gutters for buildings with a certain design solution are made - it can be copper and an alloy of titanium and zinc. The reliability, durability and appearance of such systems are beyond praise, but the price is clearly “biting”. If such systems are selected, then brackets can also be selected for them, which can be fixed to the eaves of an already roofed roof.
In principle, support brackets of different designs can be selected for drainage systems made of any material, since they are sold not only complete with the main parts, but also separately. The main thing is that the holders fit the shape and size of the gutter.
Find out how to do it by studying the instructions in a special article on our portal.
Now we need to clarify the moments when circumstances can force us to engage in the installation of the drainage system after the roofing material has been laid on the roof slopes. So, there are several reasons for this installation:
gutters
Brackets can be made of metal or plastic and vary in design. The choice of the right model will depend on the place and method of fixing the drainage system.
Brackets can be long, short and versatile:
First you need to understand the options for installing drainage systems, with a wall-mounted roof covering. This will make it possible to determine which of them is applicable in each specific case.
So, there are four ways to fix the brackets to the elements of the rafter system:
If the brackets are fixed before the installation of the roofing material, then they are most often fixed on the rafters or on the bottom board of the sheathing. In this case, support long-legged hooks that if necessary, the correct location of the grooves can be bent or they can be left straight. In addition to them, for the installation of drainage systems, in this case, universal brackets are sometimes used.
If the roofing has already been installed, for example, if the old drainage system needs to be replaced and it is planned to fix the brackets in this way, then the lower row of roofing material will have to be removed. True, this is not always easy.
To do this, it will be necessary to unscrew the fasteners not only of the first, but also of the second row of the coating. Rigid roofing material must be removed carefully. This is especially important if the coating is not new, but has been in use for several years, otherwise the sheets can be easily damaged, which will lead to unnecessary costs. And not every material lends itself to dismantling without breaking the integrity or without deformation, especially if it is fixed with nails. So, problems are very likely, for example, with ordinary slate or ondulin.
In a situation where the roof is equipped, laid on a plywood base, you can try to gently lift only the lower edge of the roofing material that runs along the eaves. Then, put the brackets on a solid crate and secure with self-tapping screws, screwing them into the rafter legs through the plywood covering. The next step is to return the bituminous tile or roofing material to its original position and fix it to the surface using bitumen mastic.
In order not to dismantle the roofing, you can try another option for installing brackets on the rafters. It consists in fixing the hooks to the side of their beam. For this, brackets with a bent, unfolded mounting platform are purchased or manufactured - an example is shown in the figure above.
It should be remembered that such installation is possible only if the rafter legs are of a sufficiently large cross-sectional size, for example, 120 × 50 or 150 × 50 mm. In addition, it must be taken into account that the hooks must be fixed so that the roofing overhangs the gutter, overlapping ½ or ⅓ of its width, otherwise water may overflow in case of heavy rain.
Therefore, if the option of fixing the brackets on the side of the rafter is chosen, then first you need to make a fitting, which will show whether this installation method is possible.
The easiest way is to install the brackets on the wind (frontal) board, and this can be done using various mounts.
The frontal board is fixed on the end sides of the rafter legs, and in various designs it can be wide or narrow. The choice of the type of bracket will depend on this parameter.
Suitable for installing the drainage system on the frontal board:
Plastic short hooks most often have a wide base in the area of the mounting platform, so they will hold the gutter firmly.
In addition to conventional brackets, you can find their adjustable options on sale. Their convenience lies in the fact that they have a special device that allows you to set the slope of the location of the hook relative to the base to which they are attached. Sometimes this function cannot be dispensed with, for example, when arranging a drainage system on an inclined wind board or on the crown of a log cabin.
bracket
Another option for attaching gutters to the frontal board using short hooks is a whole system consisting of a metal guide profile and special holding brackets. First, a guide is fixed on the wind board, which is immediately given the necessary slope. Then, brackets are put on from the side of the profile and moved along the guide, with an arrangement at the required distance. It is not necessary to fix such brackets, since they are tightly installed in the profile - this is one of the advantages of this fastening system. In addition, when mounting it, you do not have to measure the location of each hook according to its height - you just need to set the profile with the desired slope in level and securely fix it through the holes specially provided in it.
However, such a system can be installed if the roof overhang is of a suitable width.
When installing individual brackets, first a horizontal line is bounced on the wind board with a slope of three to five millimeters for each running meter of the gutter towards the drain funnel. Then, from the end edge of the frontal board, you need to retreat from 50 to 100 mm - this will be the place where the first bracket is installed.
Further, the entire line is marked so that there is a distance of no more than 600 mm between the hooks (some manufacturers' systems allow a larger step - this is stipulated in the installation instructions). In the area where the drain funnel is installed, the holders are fixed at a distance of no more than 50 mm from it.
After carrying out such a markup, you can proceed to fixing the brackets on the frontal board.
This method is applicable for installing a gutter system along the eaves of a roof covered with almost any toughroofing material... The fastening of the hooks-holders is carried out using special clamps (clamps), which fix the brackets along the edge of the roof.
There are different types of clamps, to secure some of them it will be necessary to carefully drill through holes in the roofing material, stepping at least 50 mm from its edge. Others have a construction that does not require drilling in the roof as they are clamped along the edge of the roof. This option is fixed with a screw, which, by analogy with a clamp, clamps the edge of the roof.
If the brackets will be fixed to the wave coverage, then this must be done exactly at the lower or upper point of the wave. It is recommended to put rubber gaskets under the metal fastening lugs of the clamp, both from the top and from the bottom of the roofing material, so the load on it will be slightly lower, and the compression will be softer.
For this method of installing a drain, both metal and plastic brackets are suitable. Ordinary metal long hooks can be altered by yourself, bending them in the right way, drilling holes in them and cutting threads. Plastic must be purchased ready-made.
Since in this version the entire load from the drainage system will fall on the edge of the roofing, it is necessary, if possible, to choose a set with a small mass.
In this version, an additional metal L-bracket is used to fix the short gutter holders. Its long part is fixed on the side of the rafter leg, and on the short curved shelf there is a mounting platform for fixing a short plastic holder.
This method of fastening sometimes becomes the only way to fix the brackets with a previously laid roof covering without damaging its surface. For example, if the roofing material on the overhang protrudes 120 ÷ 150 mm beyond the line of the ends of the rafter legs, and there is no desire to fix the brackets to the edge of the roof, or the coating does not provide such an opportunity.
There are other ways to install a gutter system with a previously covered roof:
If you plan to lay the gutter on pins hammered into the wall, then their installation must also be marked so that the required slope towards the funnel of the downpipe is ensured.
This type of fastening can be used to fix the gutter both on the frontal board and on the ends of the rafter legs.
If such fasteners are chosen, then the chute must be closed from above with a protective mesh, which will prevent large debris from entering it. Otherwise, fallen leaves may linger on the lintels, collecting dust and dirt flowing down with water with roofs, and over time, a cork forms in the gutter. To prevent overflow of water due to accumulated dirt, a protective mesh is needed.
By the way, you can notice that such an element of the system will not be superfluous in any drain.
Having chosen the type of brackets and the method of fixing the gutter system, before going to the store for it, you need to decide on the size of the gutter. It must correspond to the slope and parameters of the roof slope, otherwise water will overflow over its edge in case of heavy rain.
In addition, you need to decide on the cross-section of the pipes into which the storm drains from the gutter will flow, since if you purchase a pipe of not large enough diameter, it may not cope with the flows, and the water will go over the edge of the gutters - to the walls and under the foundation.
To determine the diameter, you need to decide in advance how many drainage pipes will be installed on one roof slope. There are certain standards on this score. So, if the length of the eaves of the slope is up to 12 meters, then it will be enough to install one funnel with a vertical drain pipe. With longer eaves, from 12 to 24 meters, you will have to install two pipes - at the corners of the building.
So, in order to determine the size of the elements of the drainage system, it is necessary to determine the catchment area. To do this, you need to measure the distance from the corner of the cornice to the middle of the gable side of the house - this parameter is indicated in the above diagram with the letter Y, as well as the length of the cornice line - X, and then find their product, which will determine the catchment area of one roof slope.
As you can see in the drawing, the gutter up to 12 meters in size has a slope in one direction, in the lower part of which the downpipe is mounted.
If the length of the slope is more than 12 meters, then it is necessary to find the middle of the cornice and from it two gutters sloping towards the corners of the structure, where the gutters are installed.
Slope of the gutter gutters should be 3 ÷ 5 mm for each running meter of the gutter length.
Now it is worthwhile to figure out what dimensions of the gutter and drainage pipe must be selected, taking into account the calculated catchment area.
S (area) of the catchment area, m2 | Chute section, mm. | The cross-section of the downspout with a slope of the gutter in one direction, that is, with the installation of one funnel, mm. | The cross-section of the downspout with a slope of the gutter in two directions, that is, with the installation of two funnels, mm. |
---|---|---|---|
60 ÷ 100 | 115 | 87 | - |
80 ÷ 130 | 125 | 110 | - |
120 ÷ 200 | 150 | - | 87 |
160 ÷ 220 | 150 | - | 110 |
If the catchment area is known, then to determine the dimensions of the elements of the drainage system, you can use the following table, which indicates the necessary basic parameters and shows other options for the location of the drainage system with one drain pipe.
The location of the drain pipe | Dimensions of the main elements of the drainage system | |||||
---|---|---|---|---|---|---|
Gutter -75 mm, drain pipe 63 mm | Gutter -100 mm, drain pipe 90 mm | Gutter -125 mm, drain pipe 110 mm | Gutter -125 mm, drain pipe 90 mm | Gutter -125 mm, drain pipe 63 mm | Gutter -150 mm, gutter pipe 110 mm | |
The size of the catchment area, m2 | ||||||
95 | 148 | 240 | 205 | 165 | 370 | |
![]() | 48 | 74 | 120 | 100 | 82 | 180 |
42 | 50 | 95 | 80 | 65 | 145 |
gutter
Now, having figured out the principles and methods of installing the drainage system, and how to correctly calculate the dimensions of the gutter and pipe, it is worth considering the functions of the remaining structural elements.
So, in addition to downpipes, gutters and holders for them, the drainage system consists of the following parts, each of which plays its own important role in the design:
A few words must be said about the tools that will be required to carry out the installation of the drain. It is necessary to understand correctly that the set of tools may differ depending on what material the gutter structure is made of - metal or plastic. So, for work you will need:
hacksaw for metal
In the same section, you need to immediately clarify why it is recommended to cut the elements of drainage systems using a hacksaw or metal scissors, and in no case with a "grinder" (grinder). The durability of drainage systems, both metal and plastic, directly depends on this circumstance.
When cutting with a grinder, metal or plastic heats up a lot. This leads to burnout of the anti-corrosion layer in the cutting area of the metal and melting of the plastic, which reduces the resistance of the material to external influences. For example, a polymer protective layer applied to a metal pipe or gutter can begin to peel off even up to 50 mm around the cut, making the metal virtually unprotected against moisture.
That is why it is best to listen to the recommendations of the craftsmen and cut the parts. drains only with tools that indicated above.
We believe that everything you need to install the drainage system has already been prepared. You can proceed to the consideration of installation work.
So, if the roofing cake is already installed, the most widespread An option for fixing the gutter is to fix the short holders on the wind board. Moreover It should be noted that many roofers find short hooks more reliable than long brackets. In addition, they have several other advantages:
Any installation work, including the installation of the drainage system, begins with marking the surface where the gutter brackets must be fixed. To make it easier, it is recommended that you first draw up a drainage arrangement scheme. In this case, a system with one funnel and a drainpipe will be considered.
Illustration | Brief description of the performed operation |
---|---|
![]() | The layout begins with determining the installation point of the first bracket, which will be fixed at the top of the slope. It should be located at a distance of 50 ÷ 100 mm from the edge of the wind board. Further, a nail is driven into this point, so that a cord can be tied to it. After that, using a tape measure, you need to measure the distance from the upper edge of the frontal board to the hammered nail. The same distance is determined and marked on the other side of the windboard, where the downpipe is planned to be installed. With the help of a cord, you need to beat off a perfectly horizontal line along the entire frontal board. To simplify the task, you can take a tinted paint cord. Tied to the nail, the cord is stretched along the length of the windboard to the mark made on the opposite side of it. |
![]() | Further, focusing on the drawn horizontal, you need to beat off the slope line using the same colored cord. In order to determine the specific value of the slope, which should be 4 ÷ 5 mm per running meter of the cornice, you need to determine its exact length of the slope. For example, it is seven meters. This means that at the end of the frontal board, the inclined line will drop from the horizontal by 28 ÷ 35 mm. At the end point of the line from the horizontal, the found value is measured, the second end of the cord is pressed against it, and the inclined line is beaten off. The markup can be done in a slightly different way. Having found the desired point, the bracket is immediately fixed in it, and a cord is already tied to it. The rest of the actions are carried out in the same way as in the first variant of the markup. The next step is to mark the location of the brackets on a flat horizontal line, and from it a projection is made onto an inclined line. The installation step of the holders is chosen arbitrarily, but it should not exceed 600 mm (unless otherwise specified by the manufacturer). |
![]() | The next step is to fix two brackets along the two extreme points of the marking, between which a cord is pulled, which will help to fix the intermediate holders exactly along the marked line. So, the crosshair of the projection from the horizontal line to the inclined one, as well as the stretched cord, will indicate the exact attachment point of the hooks. |
![]() | Next, the intermediate brackets are fixed. For each of them, you need to prepare two or three self-tapping screws. There may be more of them - it is recommended to use all the holes provided by the manufacturer for fixing the bracket. The intermediate brackets are installed and screwed on so that they come into contact with the cord in the same way as the outer brackets. |
![]() | After the holders are screwed to the wind board, the cord must be removed and the hooks must be checked again to ensure that they are installed correctly. The edge of the roof should hang over the gutter by ⅓ of its width so that water will flow directly into the gutter without overlapping its edge. |
![]() | Next, you need to check the distance between the roof covering and the edge of the bracket. To do this, you can put a rail on the roof and lower it from the overhang to the edge of the hook, the distance between them should be 30 ÷ 40 mm. This parameter is important due to the fact that if the edge of the bracket is lowered lower, the water flowing from the roof will overflow over its edge, and if it is raised higher, then in the spring, snow sliding from the cover, forms a cork in the groove of the gutter. In this case, the metal version of the bracket is convenient, since, if necessary, it can be slightly bent or, conversely, raised. |
![]() | The next step, according to the previously drawn up scheme, is to mark the hole on the gutter for installing the funnel and downpipe. The size of the hole must correspond to the diameter of the drain pipe. Then, along the marked lines, using a hacksaw for metal, two cuts are made at a certain angle, so that they converge at one point, as shown in the illustration. |
![]() | Further, the holes need to be adjusted - milled to the pipe diameter. This operation is performed using pliers. |
![]() | The edges of the hole are slightly bent outward - this will create a better seal when installed in the pipe hole. You need to work with pliers very carefully, trying to damage the protective and decorative metal coating as little as possible. |
![]() | The next operation - a funnel is attached to the hole in the gutter and hooks onto it with a folded edge. The other edge of the funnel has "ears" that must be bent inward of the gutter. This is done in such a way that when installing the gutter into the brackets, the bend is located on the side of the wall and be bent away from it. Thus, you get the most reliable fastening of two parts - the gutter and the funnel. Here it is necessary to clarify that in some drainage systems, a special latch is provided on the funnels, with which it is fixed on the gutter. Such a modification of this element makes installation easier, but the cost of systems with latches is also higher. |
![]() | The next step is the cutting of seals for the side gutter plug with a fixed funnel. The seal can be made of rubber or polymers, in any case, it must be flexible enough, bend easily and take the shape of a semicircle of the plug. The seals can be supplied with the gutter system, or they can be purchased separately in the same stores where the gutters are sold. |
![]() | Further, the seal must be placed in the grooves along the edge of the plug, which will adjoin the gutter. When laying it, you need to make sure that there are no gaps between the rubber and metal. First, one plug is prepared, since in the case under consideration, the second side of this gutter will be joined with another segment that goes beyond the corner. |
![]() | Then the plug is installed on the end of the gutter. Since the joint must be completely sealed, the plug with the seal installed in it can be quite difficult to put on the metal edge. In this case, a mallet will come to the rescue, for which you need to gently tap the plug from the outside, along the lower contour. Then it will fit snugly into the seat. |
![]() | Instead of a rubber seal, a roofing sealant can be used, which is applied before installing the plug on the edge of the gutter. Then, one more layer must be applied after they are combined from the inside of the gutter, at the junction of these two elements. |
![]() | It must be said that some craftsmen, for greater reliability, use both components for sealing, that is, first install the seal, and then additionally from the inside of the gutter, apply a layer of roofing sealant. Until the sealant has lost its plasticity, it is leveled with a finger dipped in soapy water. From the outside, such a seal will not be visible and will not spoil the appearance of the drain. |
![]() | The next step is to install the gutters into the brackets fixed to the wind board. Due to the fact that each section of the gutter has a standard length of 3000 mm, it is necessary to calculate in advance how many such elements are required for the entire cornice. In order not to cut the gutter with the funnel and plug installed, it should be installed first. After installing the gutter in the brackets, you need to gently press on it so that the outer fold of the holder goes under the folded edge of the gutter. There are different options for gutters in shape, but they are installed in brackets and snap into place in almost the same way. |
![]() | At the junction of two gutter segments when they are installed in brackets, a retainer is installed under the joint, which has a rubber gasket and a special lock that snaps into place on the outer edge of the gutter. Each subsequent gutter, when installed from the side of the funnel, is wound inside the previously installed one - this will ensure a free drain of water. |
![]() | The latch is wound behind the back wall of the joint and put on over its edge. From the outer edge of the gutter, it is snapped into place with a special clamp. To increase reliability, the gutter joint is covered from the inside with the same roofing sealant. Apply the sealant in a thin layer and then smooth it with your finger, as it should not obstruct the flow of water. |
![]() | This illustration shows two ways of joining two pieces of gutters or a corner element of the system, if provided by the project. The first one, described above, is the latch. And the second is the rivets that fix the retainer on the back and front walls of the gutters. However, in order to install them, you will have to prepare a special tool. If the riveter is on the list of household tools, he will greatly speed up and simplify any installation work related to thin metal. The last section of the gutter is most often shorter than the others and it is much easier to install it, but before installing it, a plug is also installed on its outer end - in the same way as shown above. |
![]() | You can strengthen the fastening of the gutter using a metal strip, which is attached with a self-tapping screw with a wide head or rivet to the front edge of the gutter, from its inner side. The second edge of the strip is fixed to the roof covering or to the wind board. In the second case, the strip will have to bend slightly. Metal strips can be cut from the remnants of a gutter or pipe. Such strengthening of the system will help it withstand high snow load and spring ice. In addition to such braces, hooks are additionally screwed onto the wind board between the brackets to hold the gutters, engaging only at the rear edge. These elements will remove some of the load not only from the holding brackets, but also from the guy wires. |
![]() | Now you can proceed to the installation of the vertical part of the gutter. The first step in the funnel installed on the gutter is to mount an elbow, which will determine the location of the vertical pipe relative to the wall. Usually you have to mount this element in order to bring the pipe closer to the wall for easier fixing. So, the pipe should be located at a distance of 60 ÷ 70 mm from the wall, since approximately this parameter is designed for a standard clamp holder. |
![]() | The elbow is put on the end of the funnel, and then the distance between it and the second elbow is measured, which determines the vertical direction of the downpipe. This is done in order to prepare a piece of pipe that will connect the two elbows. To the resulting value, add 35 ÷ 40 mm on each side, which are necessary for joining the elements. |
![]() | Further, the segment is put on top of the knee installed on the funnel, and the second knee of the structure is put on the second side of it. If you install the parts in this order, you can avoid leaks of the system at the joints of these elements. The principle is simple - any part located above must go inside the lower one. |
![]() | The next step is to determine the length of the vertical pipe, taking into account the fact that another elbow will be fixed at its lower end, which will set the direction for the water flows passing through the drain. However, it is necessary to provide for the fact that 80 mm of the resulting size will go to join the flat section of the drain with the knees. Another point that needs to be taken into account is that the standard pipe length, like the gutter, is 3000 mm, and the wall often exceeds this parameter. In this case, the pipe has to be assembled from two, and sometimes from three sections. |
![]() | Now you need to mark and mount in the wall or fix the brackets for the vertical pipe on it. They are installed with a pitch of 1200 ÷ 1800 mm, however, if the vertical pipe consists of several sections, then their joints must also be reinforced with clamps. |
![]() | However, the clamps are not mounted on the joint itself, but below it by 100 mm. The vertical pipe is installed to the wall only after the clamps are attached to it, so that after connecting the individual sections, immediately fix the drain in the brackets. |
![]() | Starting the assembly of the pipe, its upper edge is put on the lower end of the elbow installed in the upper part. Then, the bottom edge of the top pipe section is inserted into the next section. To make one section of the pipe easily fit into another, it is recommended to narrow it slightly due to bends that can be made with pliers. You need to work carefully, trying not to damage the coating. Naturally, this manipulation can only be done if the drainage system is made of metal. The plastic will crack immediately if you try to bend it in this way. |
![]() | At the end of the pipe installation, a lower elbow is put on and fixed with a bracket on its lower edge. This element is usually located at a height of 150 ÷ 300 mm from the blind area. If it is planned to install or already installed a drainage system or storm sewer under the drainage pipe, then the distance between it and the blind area can be reduced to 100 mm. And quite often the pipe completely enters the storm water inlet. |
So, the methods of installing drainage systems after covering the roof were considered. Knowledge of the nuances of the calculation and information about which fasteners are used for such structures, you can choose the best option. Such that to the maximum extent will approach the specifics of the roof structure, suit the master in terms of the complexity of execution and financial capabilities.
Frontal board version, plastic bracket mounting
The brackets are placed at the level of the cord stretched between the end bracket and the funnel. The difference in height between the end points of the cord should provide a slope of up to 3 mm per linear meter.
Option without a frontal board, mounting on a metal bracket
The option is used for roofs with a small pitch of lathing. The difference in height is provided by the bending of the bracket at the calculated place. The distance from the end of the support part of the bracket to the bending point should decrease as the intermediate bracket moves away from the final one.
Option without headboard, attachment with an extension and plastic bracket
The variant is used for roofs with a large battening pitch. The fold lines of all extensions are at the same distance. The slope is provided by sliding the plastic bracket over the extension. The bend point should be no closer than 10 mm from the attachment point of the bracket clamping plate or no closer than 10 mm from the end of the slot in the extension.
![]() |
The overhang of the roof is located above the gutter at a distance of 1/3 to 1/2 of its diameter.
The required gap between the roof extension line and the upper part of the bracket of 25-30 mm is provided by bending the final metal bracket (extension) or by moving the plastic bracket.
The distance between the gutter brackets should not exceed 600 mm. The funnel should be fixed at two points (or on two extensions). The gutter connector must be fixed at one point (or on one bracket). The end of the corner piece should be no more than 150 mm from the nearest bracket.
The distance from the plug to the nearest bracket should not exceed 250 mm.
The gutter must be inserted into the mating elements up to the line marked "Insert so far". For the convenience of installation, point micro-abutments are formed at the edges of the line, before contact with which the gutter is inserted. The distance from the end surface of the plug to the structural elements of the house must be at least 30 mm.
Before installation, the mating surfaces should be cleaned from dirt, make sure that there are rubber sealing gaskets and they are tightly installed in the slots. The gaskets must extend to the ends of the sockets. All plugs must be installed. The ends of the gutters should protrude 50 - 100 mm beyond the side cut of the roof.
The plastic bracket, funnel and connector are attached with self-tapping screws directly to the frontal board. To fix the gutter in the plastic bracket, you must first insert the edge of the gutter closest to the frontal board into the bracket clamp. Then, lowering the gutter into the receiver of the bracket and pressing firmly on the opposite edge of the gutter together with the clamp, insert the edge into the clamp until it clicks. When attaching to the frontal board, it is necessary to strengthen the connection of the board to the roof to prevent it from being pulled out under a load from snow.
Metal extensions are used for large pitch battens and are attached to the roof structure. On metal extensions, the gutter is fixed in plastic brackets. When using an extension, the plastic bracket is bolted to allow the bracket to move when the gutter slopes. A bolt (with a semicircular head) M5x30 is inserted through a washer into the upper central hole of the bracket, passes through the bracket slot and is tightened with a nut after the plastic bracket is in the required position. A washer and a spring washer must be installed under the nut. The outer diameter of the flat washers must be at least 15 mm. A spring washer is installed between the washer and the nut. To avoid vertical movements, the bracket is additionally fixed to the extension through the lower hole either with a bolt (M5x30 + 2 washers) with a hex head or with a short self-tapping screw. The funnel and gutter connector are bolted (M5x30 + 2 washers) directly to the extension. The funnel is fixed with two bolts, and the connector with one.
There are two possible fixing methods:
Pipe: fastening with slippage, on the side surface of the clamp there is an inscription "Pipe".
Fitting: fastening with rigid fixation, on the side surface of the clamp there is an inscription "Fitting".
The base of the clamp is screwed with a self-tapping screw (diameter MB, length from 50 mm) to the wall of the house. The yokes of the clamp are inserted into the base until they stop. The clamp is tightened with a round head bolt (M5, length 40 mm) and a nut.
![]() |
![]() |
![]() |
Gutter Designed to collect and drain rainwater from the roof surface |
![]() |
Gutter plug Can be installed on both the right and left ends of the gutters to ensure the tightness of the system |
![]() |
Clamp universal Designed for fixing the system to the facade of the building. Has two positions: 1. "pipe", 2. "fitting" |
![]() |
Downpipe Designed to drain water from the funnel of the gutter to the ground or into the drain |
![]() |
Funnel plug Installed on one of the ends of the funnel to seal the system |
![]() |
Tip Designed to drain water from the drainage system to the ground |
![]() |
Gutter connector with rubber seal Designed for serial connection of gutters into a single system |
![]() |
Elbow 72 ° These fittings are designed to provide a transition from funnel to pipe. They are also used to bypass architectural elements of the facade. The elbows are connected to each other with a piece of pipes |
![]() |
Bracket, plastic Designed for fixing the gutter on roofs with a frontal board or complete with an extension on roofs without a frontal board |
![]() |
Funnel Designed to connect gutters and pipes in order to drain water from the drainage system to the drainage system |
![]() |
Elbow 45 ° | Bracket metal Designed for fixing the gutter on roofs without a frontal board. Bracket support length - 300 mm |
|
![]() |
Funnel mesh (Clear Tube) Prevents leaves, needles and debris from entering the weir |
![]() |
Corner piece 90 ° Corner elements are installed on both external and internal corners of the roof and are designed to connect gutters at an angle of 90 ° (135 °) in order to change the direction of water movement |
![]() |
Extension metal Designed to secure a plastic bracket for roofs without a headboard. The length of the support part of the extension - 240 mm |
![]() |
Coupling connecting Designed to connect a pipe with a funnel or two pipes |
![]() |
Corner piece 135 ° |
Such an important architectural element of the roof structure, which is the drainage system, must be thought out even at the design stage. Moreover, modern SNiPs recommend installing the system even before installing the roof covering. However, in reality, not everything is so smooth.
Sometimes circumstances force the installation of a drainage system if the roof is already ready. Accordingly, it will not be superfluous to find out how to install gutters if the roof is already covered.
Several situations are possible when the need for such an installation arises:
You can also try another option for fixing the hooks to the rafters. The brackets are fixed to the side edge of the rafter bar. The mounting surface of the holders is bent horizontally (this operation can be performed independently). This type of installation is possible only when the cross-section of the rafters is large enough, for example, 12 or 15 * 5 cm. When fixing the brackets, it is important to take into account that the roof covering should overlap the gutter by half or a third of its width. Then you can not be afraid that as a result of heavy rainfall, water will overflow over the edges of the gutter.
Obviously, when installing the brackets on the side edge of the rafter, preliminary fitting is required. In the process of trying on, it will become clear whether such an installation option is possible.
For those who are wondering how, if the roof is already covered, it is important to know that the simplest installation option is the frontal board.
On a note
It can be easily decorated to make the board look like a stand-alone roof exterior detail.
Pick up short hooks made of the same material. It is also desirable to fix them on metal. Their low weight allows them to be fixed to a wooden wind board without any difficulties.
Separate mention is made of adjustable brackets equipped with a special device. It shifts one relative to another part of the bracket, which sets the slope of the holder location, that is, the angle that forms the hook and the base for the fasteners. To obtain the required angle, all you need to do is tighten the adjustment screws. Such brackets are practically indispensable for use in difficult conditions, for example, if the windboard is inclined.
After that, brackets are threaded from its lateral side and advanced along the guide, placing them with the required step. It is noteworthy that such holders do not need to be fixed, since they “sit” quite firmly in the profile. Undoubtedly, this is another advantage of such a fastening system.
Sometimes there is no wind board in the roof structure at all. Then they resort to using special "crutches" made of metal or wood, fixed in the wall. The grooves are attached directly to the "crutches" on pins or bars.
This method is justified when fixing the roof drainage system along its eaves. This option is suitable for almost any roofing material. The brackets are fastened using clamps (this is how special clamps are called).
If the system is fixed to a wave material, then the holders are attached either to the lower or upper point of its wave. In this case, it is advisable to lay rubber gaskets under the legs of metal clamps on both sides of the roofing sheet. Thus, you can solve two problems at once: to slightly reduce the load and soften the compression on the sheet.
When using the above option for installing gutters, you can also use short hooks, but with one condition. In addition to these, L-shaped metal brackets are required. Their long part is fixed on the side edge of the rafter. As for the curved shelf with a mounting platform on short parts, a short PVC holder is fixed to it. It should be noted that in some cases this is the only way to fix the holders to the previously laid roof without damaging it. For example, if the roof protrudes beyond the ends of the rafters on the eaves overhang of the order of 12-15 cm.
The construction market also offers brackets that hold the gutter from above, as opposed to the traditional version from the bottom. They are completely invisible after installation. Such holders are fixed at a distance of 400 - 700 mm between them. If this condition is violated, there is a high probability of significant deformation of the gutter, caused by the effect of a significant load of ice or snow gravity.
The brackets, which are used when installing to the crate, or from above to the rafters, must first be bent. In this way, the holder is given the desired shape, which allows it to subsequently be ideally adjusted to the slope of the slope.
The pendant mount is less popular than the above options. However, in some cases, such a design is the only possible way. This type of bracket has special bends. During installation, one of them is put on the front edge of the gutter, while the second is hooked on the back. The holder is provided with a sleeve having an internal thread. The fastening element is screwed into the wall or wind board through the bushing and the upper section of the gutter wall.
On a note
When marking the location of the pins, the necessary slope must be provided in the direction of the funnel of the drainage system.